Note 19 – Commitments and contingencies

 

On May 28, 2019, the Company and Mentor Partner I, LLC filed suit against the G Farma Entities and three guarantors to the G Farma agreements, described in Notes 1, 7, and 8, in the California Superior Court in and for the County of Marin. The Company primarily sought monetary damages for breach of the G Farma agreements, including promissory notes, leases, and other agreements, as well as actions for an injunction to recover leased property, to recover collateral under a security agreement, and to collect from guarantors on the agreements. Due to uncertainty of collection, the Company has recorded reserves against the finance leases receivable described in Note 8 and has fully impaired all other notes receivables and investments in G Farma described in Notes 7 and 8.

 

On November 13, 2019, G Farma filed a Cross-Complaint for declaratory relief and breach of contract relating to the consulting agreement between Mentor and G Farma. The Company filed an answer on December 6, 2019, denying each and every allegation.

 

On January 31, 2020, all remaining equipment leased to G Farma by Mentor Partner I, which was not impounded by the Corona Police, was repossessed by the Company, and moved to storage under the Company’s control. In the quarter ended March 31, 2020, the Company sold a portion of the recovered equipment, with an original cost of $495,967, for net proceeds of $222,031. In the quarter ended June 30, 2020, the Company sold all remaining recovered equipment, with an original cost of $126,703, for net proceeds of $27,450, after deducting shipping and delivery costs. All proceeds from the sale of repossessed equipment were applied to the G Farma lease receivable balance.

 

On July 2, 2020, Mentor Capital, Inc. and Mentor Partner I, LLC filed a motion for summary adjudication seeking judgment on four of its sixteen causes of action related to breach of the Promissory Notes and the related guarantees.

 

On November 4, 2020, the Court granted Mentor Capital, Inc.’s and Mentor Partner I’s motion for summary adjudication as to all four causes of action: both causes of action against G FarmaLabs Limited for breach of the two promissory notes totaling $1,166,570 and one cause of action against each of Mr. Gonzalez and Ms. Gonzalez related to their duties as guarantors of G FarmaLabs Limited’s obligations under the promissory notes.

 

 

Mentor Capital, Inc.

Notes to Consolidated Financial Statements

December 31, 2021 and 2020

 

On August 27, 2021, the Company and Mentor Partner I entered into a Settlement Agreement and Mutual Release with the G Farma Entities to resolve and settle all outstanding claims (“Settlement Agreement”). The Settlement Agreement requires the G Farma Entities to pay the Company an aggregate of $500,000 plus interest, payable monthly as follows: (i) $500 per month for 12 months beginning on September 5, 2021, (ii) $1,000 per month for 12 months beginning September 5, 2022, (iii) $2,000 per month for 12 months beginning September 5, 2023, and (iv) increasing by an additional $1,000 per month on each succeeding September 5th thereafter, until the settlement amount and accrued unpaid interest are paid in full. Interest on the unpaid balance shall initially accrue at the rate of 4.25% per annum, commencing February 25, 2021, compounded monthly, and shall be adjusted on February 25th of each year to equal the Prime Rate as published in the Wall Street Journal plus 1%. In the event that the G Farma Entities fail to make any monthly payment and have not cured two such defaults within 10 days of notice from the Company, the parties have stipulated that an additional $2,000,000 will be immediately added to the amount payable by the G Farma Entities.

 

On October 12, 2021, the parties filed a Stipulation for Dismissal and Continued Jurisdiction with the Superior Court of California in the County of Marin. The Court ordered that it retain jurisdiction over the parties under Section 664.6 of the California Code of Civil Procedure to enforce the Settlement Agreement until performance in full of its terms.

 

The Company has retained the reserve on collections of the unpaid lease receivable balance due to the long history of uncertain payments from G Farma. See Footnotes 7 and 8 for a discussion of the reserve against the finance lease receivable.

 

For G Farma notes receivable we will continue to pursue collection of the settlement payments from G Farma, its affiliates, and the guarantors of the various G Farma note purchase agreements that are fully impaired at December 31, 2021 and 2020, see Note 7. We will continue to pursue collection for lease payments remaining, after applying proceeds from the sale of recovered assets, that are fully impaired at December 31, 2021 and 2020, from the G Farma Lease Entities and G Farma Lease Guarantors, see Note 8.